|
|
 |
|
 |
| |
| |
Reprinted
From Engineered Systems Magazine
P.O. Box 4270 Troy, MI 48099 Copyright
2001
Click
here to download PDF |
 |
 |
|
Boiler replacement
Brews up 15% Savings for Labatt
Labatt
Breweries Ontario is a division of Labatt Breweries
of Canada, which was founded in London, Ontario
in 1847. As one of the nation's longest-established
and most successful brewing companies, Labatt
brews 60 quality beers in eight breweries from
coast to coast and distributes in 40 countries
internationally. One of the company's largest
breweries is in Toronto. The plant's 350 employees
work three shifts and in some 500,000 sq ft,
they produced roughly 52 million gal of suds
last year.
In the summer
of 2000, the facility's plant manager, Robert
Bowman, decided it was time for the plant's
30-pluls-year-old secondary water tube boiler
to go. While the plant has primary boiler that
carries about half the load, the boiler Bowman
wanted to replace served mainly as a backup
and covered weekend loads. Some of the secondary
unit's tubes had been removed, it didn't have
an economizer, it had refractory problems, and
its skin had been repaired a number of times.
"The desire
to increase energy efficiency was a major part
of the decision. The boiler served as our weekend
load as well as a backup for the main boiler,
and its combustion efficiency on the high end
was OK, but on the low end, the radiation and
combustion losses put in the low 60% for thermal
efficiencies, he said.
WEIGHING THE OPTIONS
Bowman contemplated
a number of options. First, he considered selection
a cogeneration unit that would produce electricity
and steam, but the capital investment involved,
combined with cost of natural gas, made I prohibitive.
Next, Bowman pondered the option of retrofitting
the boiler. However, changing the tubes and
refractory; and upgrading the combustion controls
would have been costly and the unit still would
have inefficient on the lower end of operation.
He also thought
of replacing the unit with a new, or even used,
larger water tube boiler of the same type. That
idea was shot down because it was cost prohibitive,
and also because the existing boiler was basically
landlocked in the building. Putting a similar
unit that space would have required removing
part of the roof and lowering it in from above.

|
 |
|
|
"So
it came down to replacing it with smaller units
that we could bring through the doors,"
Bowman said, adding that this familiarity with
the Miura EX 300 BHPS from his previous job
also made the decision easier. He had selected
Miura boilers when he worked as Engineering
Services Manager with E.D. Smith (a food processor
of jams, ketchup, salsas, pasta, and various
other sauces). In that situation, the installation
facilitated a staff reduction since Canadian
requirements for boiler operators are tied to
boiler size. By installing compact Miura boilers
he reduced his staff requirement from three
operating people per day (one each per three
shifts) to only one day-shift person on at a
time. This person's role became more focused
on accomplishing maintenance.
LOW-END EFFICIENCY
ACHIEVED
Easing the operating
staff wasn't the objective at Labatt. The project
was justified on a payback of energy savings,
bowman said. "it would allow us to have
a higher and lower-end efficiency and the multiple
units would be able to handle increasing loads,"
he added. The installation, which was performed
by a local contractor, Gimco (Markham, ON),
went relatively smoothly.
One of the main
tasks was tearing out the existing boiler, and
that went off without a glitch. Bowman said.
One of the only challenged involved in the installation
was that the boilers were delivered upright,
when in order to get through the plant's doors,
they had to be turned on their sides. However,
there were no other significant problems.
|
 |
The
installation was complete in August 2000 and
the results have impressed Bowman. The new Miura
units now carry about 40% of the plant's need.
"We operate these boilers a the time to
supplement our primary boiler to maximize our
efficiencies. They run 30,000 lb/hr-900 bhp
(boiler horsepower,)" Bowman said.
"There was
about a 15% reduction in fuel for equivalent
loads, and we have been getting good efficiencies
on weekend that we never realized before. We
could probably justify the addition of another
300 hp and 200 hp - they would give us more
backup power and the smaller unit would better
handle the smaller loads," he added. ES

|
|
|
|
 |
©
2006 Miura Boiler Co., Ltd.
Website by Digital Duck Inc. |
| |
|