|
Boiler Work Heats Up Savings at DuPont
DuPont Canada Inc, an Industrial Energy Innovator,
continues to lead in its efforts to reduce energy
costs and consumption. The latest example of DuPont's
energy efficiency initiative can be found at its Customer
Technical Centre (CTC) in Kingston, Ontario, where
recent boiler work is expected to result in annual
energy cost savings of $220,000.
The centre, supplied with services from the main
site located approximately 300 m (1000 ft.)
away, houses a number of textiles labs and some research
facilities as well as members of the corporate procurement
group, central engineering and DuPont's main engineering
contract partner, Fluor Canada Ltd.
Various problems with the steam supply over the past
10 years include numerous leaks from the insulated,
8-inch, 250-psi steam line located underground.
Heat loss through 300 m (1000 ft.) of underground
piping was substantial as it was discovered that the
pipe insulation had mostly deteriorated.
 |
 |
| |
DuPont could easily trace
its steam line in winter, as the ground was never
frozen and the grass grew year-round. Steam is
used mainly for heating buildings. |
| |
 |
In the winter, the ground temperature above the steam
line has been measured at 2025°C where the
pipe is 3 metres (10 feet) below grade,
and as high as 8590°C at a point where the
pipe enters the CTC building at 1 metre (3 feet) below
grade. Steam flow during the summer when there
are no users at the CTC has been measured at
9071360 kg (20003000 lbs.) per
hour. With flow increasing in the cooler months, DuPont
has estimated heat losses at up to 7175 kg (7000 lbs.)
per hour of 250-psi steam.
Owing to the distance from the plant to the CTC building,
DuPont does not recover any condensate from this location,
which resulted in a further loss of both heat and
treated water. The cost of digging up the line, replacing
it and re-insulating it was exorbitant. The solution
was to use the steam and condensate savings to pay
for the installation of small local boilers (and to
recover the condensate) to supply the CTC's needs.
 |
|
| New boilers installed
at DuPont's Customer Technical Centre in Kingston,
Ontario, are expected to result in annual energy
savings of 33 000 GJ per year. |
 |
| |
 |
The project, with a cost of $1.2 million, was considered
a perfect fit under DuPont's Performance Contract
Master agreement. Annual energy savings, steam plus
recovered condensate, are estimated at 33 000 GJ
per year with an attendant 1780 tonnes reduction
of greenhouse gases per year. Constructed in 2002,
the project came on-line January 8, 2003.
The old steam line was isolated on January 9
at the main plant to start the energy savings.
|